Project timeline
How a cabinet project comes together
Six steps from your first design meeting to installation, coordinated with your builder’s schedule.

Step 1: Schedule Your Design Meeting
Best time: foundation or early framing
Meet with us to review your cabinet layouts and begin making selections.
Step 2: Finalize Your Selections
During framing
Finalize layouts, materials, colors, door styles, crown, knobs and pulls, appliance model numbers, and specialty sink information.
Step 3: Review Drawings and Pricing
We send updated drawings and pricing to you and your builder.
Review everything carefully and request any final changes.
Two revision rounds included
We’ll work through changes during your design meeting, followed by one final revision after you receive updated drawings and pricing. Additional revisions may require design or estimating fees.
Step 4: Final Approval
Target: by roof trusses
All layouts, selections, and cabinetry related specifications must be finalized and approved before production can begin.
Step 5: Build and Finish
Typical production: approximately 9 weeks after final approval
Materials and doors have lead times. We then cut, build, paint or stain, and prepare your cabinetry for installation.
Delayed final approval may affect whether cabinets are ready for the scheduled installation.
Step 6: Cabinet Installation
Installation timing is coordinated with your builder based on the construction schedule.
After cabinet installation, countertop templating, flooring, appliances and final cabinet details follow.
Start a conversation
Ready to schedule your design meeting?
The best time to meet is at foundation or early framing. Tell us about your project and we’ll be in touch.